Q and A’s About Helical Piles & Helical Tie-Backs
I hear a lot about different helical pile systems. What sets A.B. Chance apart from the rest?
A.B. Chance has been manufacturing helical anchoring products longer than any other helical pile manufacturer. Their products have the recognition and acceptance of all the major U.S. building codes.
Aren't most of the helical products in the marketplace comparable in their capabilities?
Some helical pile contractors advocate pipe-based products, while others believe in solid square-shaft helical hardware. Which is better?
Should I be concerned about corrosion and corrosion protection when I'm considering steel foundation support piles?
Yes, particularly in situations where there is new construction in poorly-consolidated fill material. Ultimate settling of soils under and around footings, grade beams and floors creates air-spaces which can also harbor water – providing a haven for rust and corrosion. Stand-alone structures supported on helical piles, such as walkways, docks and machine bases can leave exposed shafts vulnerable to corrosion at the ground line. In these situations, hot-dip galvanized helical piles are a must.
Why do solid square-shaft helical piles offer greater resistance to corrosion?
Unlike hollow, pipe-based products, solid square-shaft piles can corrode only from the outside inward. With hot-dip galvanizing and the addition of a drawn-down grout column, any potential for corrosion is all but eliminated.
Aren't most helical piles components furnished with some kind of serious corrosion protection?
Not necessarily. Some are coated with clear lacquer, painted or powder-coated. Some are even sprayed with silver paint to appear as though they’re galvanized. Make sure you ask!
I have quotes from different contractors who are proposing varying numbers of steel piles to support the same area of my building. Who is correct?
There is no exact science to designing underpinning or new construction support with helical piles. The ability to save money on piles by increasing the span between them depends upon the weight and integrity of the structure. Another factor is the engineer’s and/or contractor’s comfort level with the design and their willingness to offer a long term warranty. More support piles of comparable capacity within the same area translates to a greater margin of safety. If a contractor is proposing a project with significantly fewer support piles, he should have the engineering and warranty to back it up and there should be a significant bottom-line cost savings to you.
I have an existing building that's experienced considerable settling. There are sizable cracks and the floor is out of level. One contractor claims he can close the cracks and "level everything up". The other is apprehensive about promising such an outcome and is advising me to exercise caution. Who is right?
Be careful about awarding an underpinning contract to a contractor based upon their promise of a lifted, “leveled” structure. In most cases, it’s much safer and more realistic to lift slightly to stabilize a structure in place than to attempt major corrective jacking using steel piles. Over-zealous jacking can create peripheral and hidden damage, as well as lifting portions of the building beyond the boundaries of the underpinning piles, setting the stage for future movement in those newly-unsupported areas.
Get in Touch
Open Hours
Mon-Fri: 7:30 a.m. - 5:00 p.m.
Sat-Sun: Closed
Our Office
10370 Baltimore National Pike
Ellicott City, MD 21042
Contact Us
Call Levelift Foundations, LLC to discuss all your foundation repair and new construction needs at 410-480-4848 or fill out our form below.